School Rebuild March 2019

The rebuild is continuing to progress well despite the challenge of the weather last week.  A sufficient electrical supply has been laid from Mersey Road to ensure the new school can cope with the electrical demands of the modern era.  Drainage works have been continuing along the front of the new school and will ultimately meet up with the local drainage on Poplar Street.  The external boarding is now starting to be erected which will then allow the insulation and brick work to begin before the windows are installed.