School Rebuild February 2019
The rebuild continues to progress well, the bulk of work the last couple of weeks has been at ground level, preparing the sub floor with various membranes in preparation for the concrete being poured in the near future. the first floor is also ready to have its concrete base poured as the metal decking is now down.
Drainage work has also taken place with new manholes being installed and the internal drainage laid before the concrete floor slab goes in. Fortunately the snowy weather a couple of weeks ago did not cause any delays.